A fully restored northern pontoon is back in place at the Tūtūkākā boat ramp, returning it to the two-sided configuration that regular users have been doing without for several seasons.
The deterioration of the old northern pontoon had eventually forced its removal, leaving the facility operating from the southern side only. Given that Tūtūkākā is among the most-used departure points for the Poor Knights, that reduced capacity meant congestion and frustration during peak summer periods.
With the new structure now complete, the ramp is fully operational again. For the boaties who use it regularly, the change is a straightforward one: less pressure on busy days, and a faster, safer experience when launching and retrieving.
*Built by locals who know the coast*
Whangārei District Council contributed funding to the project, but the hands-on work was carried out largely by local marine contractors and businesses with deep familiarity with the harbour and surrounding coastline.
Infrastructure Committee chair Brad Flower said the outcome demonstrates what community backing can achieve.
"This is a real win for the community. The new pontoon will make a big difference for locals and visitors, thanks to the hard work of local contractors and community support."
The range of Northland businesses involved in the project was considerable. Johnson Bros Marine Construction handled the design, managed the consenting process, and drove the piles using a Bay of Islands barge. Heron Construction cast the six concrete pontoons at their Lower Port Road facility. Steve Bowling Contractors and Robinson Asphalts provided crews, machinery, and project oversight. BDC Concrete constructed the abutment that ties the floating structure to shore. Yendell Electrical and Ken Topp Builders handled the electrical work and final finishing. Atlas Cranes carried out the precision heavy lifts needed to position the six-tonne pontoons.

Beyond their labour, many of these businesses contributed financially as well, donating materials, equipment, and direct funding. Council described the level of private contribution as "extraordinary".
*A practical win for a busy boating hub*
For the Tūtūkākā community, the upgrade does more than patch a gap. The ramp now has the capacity it was originally designed for, easing the bottlenecks that build on high-traffic days and making day trips to the outer coast more straightforward for everyone who uses it.
As summer approaches, those who launch here regularly are expecting shorter queues, less tension at the ramp, and a noticeably smoother operation all round. For one of Northland's most popular boating gateways, the scale of the work was modest but the practical difference is anything but.