Rt Hon Winston Peters Ferry Announcement

Breaking news: Winston Peters, Minister for Rail announces Rail ferries and infrastructure solution

2 min read

Cabinet today agreed on the package which Mr Peters says will deliver the appropriate ships and infrastructure for the job at a significant saving for the taxpayer.

“Our solution will be markedly cheaper than the cancelled $3.1 billion programme and the $4 billion warning the previous Government received. That’s because of a minimum viable and maximum reuse approach for the port infrastructure,” Mr Peters says.  “The future Interislander ferries will have road and rail decks, given the efficiency of single shunt movements for multiple rail wagons for loading and unloading.

“The design specifications chosen include vessel lengths of approximately 200 metres – longer and wider than the current fleet and capable of serving our people and goods into the future, but shorter than the large ferries ordered in 2021 which created significant infrastructure issues.”

Mr Peters says in addition to selecting the appropriate rail ferry specifications, getting the infrastructure right is essential for a cost-effective solution.  “The marine infrastructure in Picton requires replacement, so it will be replaced. The marine infrastructure in Wellington has life left in it, so it will be modified and re-used.

“Our analysis showed this to be the most cost-effective option, and contrasts sharply with the wanton demolition and extravagant specification under the cancelled project, where they assumed almost all costs would be at the taxpayers’ expense. We are extraordinarily grateful to our small Ferry Holdings team and the hard work put in across the three companies,” Mr Peters says.

Along with the announcement, graphics of impacted land-side infrastructure were released. Here its possible to see, in Wellington, the impacts on the existing and new-build infrastructure required for loading, unloading and managing the ferries.
Along with the announcement, graphics of impacted land-side infrastructure were released. Here its possible to see, in Wellington, the impacts on the existing and new-build infrastructure required for loading, unloading and managing the ferries.
Along with the announcement, graphics of impacted land-side infrastructure were released. Here it's possible to see the impacts on the existing and new-build Picton infrastructure required for loading, unloading and managing the ferries.
Along with the announcement, graphics of impacted land-side infrastructure were released. Here it's possible to see the impacts on the existing and new-build Picton infrastructure required for loading, unloading and managing the ferries.

Now that the mode and specifications have been selected, the Ferry Holdings Board will shortlist shipyards to compete on price and quality, with a ferry contract awarded later this year. Ferry Holdings will also work with Port Marlborough, CentrePort and KiwiRail to finalise the scope, progress engineering, strengthen the delivery programme and agree co-funding terms.

Key specifications of the new ferries

  • The new ferries will be approximately 200 metres long and 28 metres wide.
  • The ferries will have the capacity for 1,500 passengers, and 2.4 kilometres of lanes for cars, trucks, and 40 rail wagons, on each.
  • A key design consideration was to ensure they can operate through the Tory Channel, operate at a speed of 20 knots and be highly manoeuvrable.
  • Most importantly, the new ferries will be designed with modern systems, redundancies and future-proofing solutions to reduce carbon emissions.

Key dates for the project

Ships Procurement

Commence ship procurement with shortlisted shipyards  April
Key ship procurement advisors (e.g. naval architects, lawyers, broker) appointed  April
Request for Proposal response due back from shipyards   June
Letter of Intent signed with preferred shipyard  Q3 2025
Ship contract negotiation  Q3 2025
Ministerial decisions on ship contracts  Ship contracts executed  Q4 2025

Port Infrastructure

Multi-party commercial negotiations commence  Q2 2025
Commercial Agreements reached on multi-party infrastructure scope, costs and programme schedule  Q3 2025
Enabling works commence  Q3/Q4 2025
Ministerial decisions on infrastructure funding  Port and other party agreements executed  Q4 2025

Ferry Holdings

Ferry Holdings assumes full responsibility for the project from the Treasury  Interim management team in place  Engagement of critical advisors commences  April 2025
Ferry Holdings led governance structures in place with Ports and KiwiRail  Q2 2025
Business case for funding and implementation   Q3 2025